UPDATE - Lower Village Paving Project - May 2022 -- BEGINS 5/9/2022

5/5/2022

Villagers –

The Lower Village Paving Project is scheduled to begin on Monday May 9th along the route outlined in this flyer and will follow this general schedule:

  • 2 days for grinding/cleanup (5/9 - 10, starting at SE 27th St)
  • 2 days for overlay paving (5/11 - 12)
  • 1 day to pave back berms and speed bumps (5/13)
  • 2-3 days to adjust utilities, perform any necessary edge/property restoration (5/16 - 18)