2019 Water Main Replacement Project

Project Work Zone

Project Work Zone

For the past two years, the Beaux Arts Water Department has been discussing and planning for a water-main replacement project along the following streets:

  • on 103rd Ave SE from SE 27th Street to SE 28th Street,
  • on SE 28th Street from 102nd Ave SE to 103rd Ave SE, and
  • on 102nd Ave SE from SE 28th Street to SE 28th

The Water Department has hired Bonner Bros Construction to dig a trench in the roadway, lay the new water main, disconnect and re-connect individual water service lines, and cover and repave the trench.

To perform this work, the contractor will need ALL vehicles moved away from the roadway in the work zone during the day; however, access to homes will be restored every night. There will be interruptions in water service during the days when the contractor is disconnecting and reconnecting services.

Construction is slated to begin in early August 2019. Throughout the project duration, Bonner Bros will work to keep interruptions to a minimum, and your cooperation will help ensure that this project is completed during the month of August when many Villagers are away on vacation.

The Water Department will post updates as construction details become available.

Contact Info

Stacia Schroeder
Town Engineer
townengineer@beauxarts-wa.gov

Bob Durr
Water Dept Supervisor
(Check your Green Book)